Project Name: BHP WAIO – Operation and Maintenance of OHP4 Scope: Contract Mining – Production (Crushing & Screening) and Maintenance of Fixed Plant Volume: / TMM 9 Mtpa Duration: 5 years, commenced August 2022 Description:
Partnered with CSI.
Crushing and Screening of Iron Ore.
Daily tonnes target 27,825.
Day shift and Night shift crew.
All fixed plant maintenance – mechanical, electrical and fabrication.
Shutdown maintenance.
Indigenous Traineeship for Cert III in Resource Processing, to date 4 graduate indigenous trainees.
Crew of 39 People split evenly between PMWI and CSI.
December 2022 the plant hit a new record of tonnes crushed in a 24 hr shift out at MAC for OHP4 of 30,260.